Success story
DURING THE COMPANY'S WORK, A NUMBER OF ENERGY PROJECTS WERE IMPLEMENTED.

07
10-2016

WPS Staryi Sambir-1 - Phase II

Commissioning of the second phase for wind power plant Staryi Sambir -1 totaling 13.2 MW

29
12-2015

Sambir SPS-2 - Phase IV

Completion of the construction and operation of the forth phase for a 5.082 MW  solar power plant Sambirska-2

07
12-2015

Sambir SPS-2 - Phase III

Completion of the construction of the third phase for a 5.082 MW solar power plant Sambir SES -2

12
12-2014

Rava-Ruska heat station

The first boiler-house on biofuel Rava-Russian thermal power plant was put into operation. There are currently four boiler houses with a total capacity of 2.16 MW.

08
12-2014

WPS Staryi Sambir-1 - Phase I

Commissioning of the first phase of a 6.6MW wind power plant Staryj Sambir -1

01
10-2013

Sambir SPS-2 Phase II

Operation of the second stage of a 2.02 MW solar power plant Sambirska-2.The total capacity of the station is 3.1 MW

26
06-2013

Sambir SPS-2 Phase I

The Construction of the first phase of a 1.081 MW solar power plant Sambirska-2 is completed

20
05-2013

Sambir SPS Phase II

The second stage of the Sambir SES with the capacity of 2,02 MW is launched. The total capacity of the station is 3.1 MW.